Construction joints are required when the concreting has to be stopped for the day or more than 30minutes. In such case, typical construction joints shall be provided so that bond is maintained between set concrete and fresh concrete. Below are some images showing correct method of construction joints to be provided in columns, beams and beam-column junction. To know about what is construction joint, read Joints in Concrete Construction.
1. Construction Joint in Column
Following figure shows correct method of providing construction joint in column. Construction joint in column shall not be provided with smooth surface or inclined surface. The top surface of the column should be rough with parts of coarse aggregates being seen.
Fig: Typical Construction Joint in RCC Column
2. Construction Joint in Beams and Beam-Column Joint:
Following figure shows the typical construction joint to be provided in beams and beam column joints.
Fig: Typical Construction Joint in Beams and Beam-Column Joint
The
arrow symbol shows the direction of concreting, tick mark shows the
correct method of providing construction joint while cross-mark shows
the wrong method.